IBPS RRB PO Time & Work Questions
Top 2 PYQs (2023–2023) — with Solutions & Shortcuts
IBPS RRB PO Time & Work is one of the most frequently tested topics — 2 previous year questions from 2023–2023 papers are included on this page. Each question comes with a step-by-step solution, common trap identified, and a time-saving shortcut.
A task requires 120 person-days of work. Worker M can complete it in 30 days, and worker N can complete it in 40 days. M and N work together for 10 days, then M takes a 5-day break while N continues. After M returns, both work together until completion. What is the ratio of wages earned by M to N if they are paid proportionally to work done, and the total wage is ₹12,000?
A project is divided into two parts: Part A requires 60 person-days and Part B requires 40 person-days. Worker X completes Part A in 12 days and Part B in 10 days. Worker Y completes Part A in 15 days and Part B in 8 days. If X and Y work together on Part A for 4 days, then X alone finishes Part A, and Y alone finishes Part B, what is the ratio of time taken by X to complete his remaining work to the time taken by Y to complete her remaining work?
🔓
12+ more Time & Work questions in the Practice Panel