Work is always considered as 1 unit (complete job). If A can complete work in 10 days, A's rate of work is 1/10 per day. This means A completes 1/10th of the total work each day
๐กKey Rules
Work = Rate ร Time. If multiple people work together, their rates add up. Total work is always 1 unit. Rate of work = 1/Time taken to complete the job
๐Basic Formulas
- If A completes work in 'a' days, A's one day work = 1/a
- If A and B together complete work in 'd' days, (1/a + 1/b) = 1/d
- Time taken by A and B together = (a ร b)/(a + b) days
- If A completes work in 'x' days and B in 'y' days, working together they complete in xy/(x+y) days
๐
Exam Patterns
What examiners ask โ read before attempting PYQs
๐Common patterns include
two people working together, one person leaving midway, comparing efficiencies, and alternative work scenarios
โกShortcut Trick - LCM Method
Take LCM of all time periods given. This becomes total work. Then find individual rates by dividing LCM by individual time. This eliminates fractions and makes calculations faster
โ๏ธWorked Example 1
1
A's one day work = 1/12
2
B's one day work = 1/18
3
Combined one day work = 1/12 + 1/18 = (3+2)/36 = 5/36
4
Time taken together = 36/5 = 7.2 days
Alternative (Shortcut): Time = (12 ร 18)/(12 + 18) = 216/30 = 7.2 days
Worked Example 2: A and B together can complete work in 6 days. A alone can complete it in 10 days. In how many days can B alone complete the work?
1
Combined one day work = 1/6
2
A's one day work = 1/10
3
B's one day work = 1/6 - 1/10 = (5-3)/30 = 2/30 = 1/15
4
B alone can complete work in 15 days
Shortcut Formula: If A and B together complete work in T days and A alone in A days, then B alone takes: B = (A ร T)/(A - T) days
Applying: B = (10 ร 6)/(10 - 6) = 60/4 = 15 days
Most Common Trap: Students often add time instead of adding rates. Remember - when people work together, their RATES add up, not their TIME. If A takes 4 days and B takes 6 days, together they DON'T take 4+6=10 days. Instead, calculate 1/4 + 1/6 to find combined rate
โ ๏ธAnother Major Mistake
Forgetting that work is always 1 unit. Students sometimes assume work quantity changes, leading to wrong calculations. Always treat complete work as 1 unit regardless of the scenario
โกEfficiency Trick
If A is twice as efficient as B, then A takes half the time B takes. If A:B efficiency ratio is 2:3, then their time ratio is 3:2 (inverse relationship)
โNegative Work Concept
Sometimes one person does work while another undoes it (like filling and emptying a tank). In such cases, subtract the rates instead of adding them.
If 8 workers can build a wall in 6 days, how many days will 12 workers take to build the same wall?
Practice 2easy
If 5 workers can build a wall in 18 days, how many days will 9 workers take to build the same wall (assuming all workers work at the same rate)?
Practice 3hard
A and B together can complete a project in 12 days. After working together for 4 days, A leaves and B completes the remaining work alone in 10 more days. In how many days can A alone complete the entire project?
Practice 4hard
Pipes A and B can fill a tank in 20 hours and 30 hours respectively. Pipe C can empty the full tank in 40 hours. If all three pipes are opened simultaneously, and after 5 hours pipe A is closed, how many more hours are needed to fill the tank?
Practice 5hard
X can do a job in 12 days, Y can do it in 18 days, and Z can do it in 36 days. They work together for some days, then Y and Z continue while X leaves. After X leaves, Y and Z work together for 6 more days to finish the job. For how many days did all three work together?
Practice 6hard
A contractor hired A, B, and C to complete a project. A works at 3 times the speed of C, and B works at 2 times the speed of C. If all three working together can finish the project in 8 days, how many days will it take for B alone to complete the project?
60-Second Revision โ Basic Time & Work
Formula: Combined time = (a ร b)/(a + b) for two people working together
Remember: Add RATES, never add TIME when people work together
Trap: Don't assume 4 days + 6 days = 10 days together
Quick method: Use LCM of times as total work to avoid fractions
Efficiency rule: Higher efficiency = Less time (inverse relation)
Standard approach: Find individual rates, add them, then find combined time
Check: Combined time should always be less than individual times