RRB NTPC Time & Work is one of the most frequently tested topics — 14 previous year questions from 2018–2021 papers are included on this page. Each question comes with a step-by-step solution, common trap identified, and a time-saving shortcut.
A job requires 120 worker-days to complete. If 5 workers are assigned to the job, how many days will it take to finish?
Q5Exam PatternEasy
The work efficiency of A is 3 times that of B. If A and B together complete a project in 9 days, how many days will B alone take to complete the project?
Q6Easy
A worker can complete a job in 12 days. If he is paid ₹480 for the entire job, what is his daily wage?
Q7Exam PatternMedium
Three workers P, Q, and R are paid in the ratio 3:4:5 for a job. If the total payment is ₹14,400 and they work for 8, 10, and 12 days respectively, what is Q's daily wage?
Q8Exam PatternMedium
Pipe A can fill a cistern in 12 hours, and Pipe B can empty it in 18 hours. If both pipes are opened together, how long will it take to fill the cistern?
Q9Exam PatternMedium
A and B are paid in the ratio 3:2 for a project. If A receives ₹9,000 for completing 3/5 of the work, what is B's wage for completing the remaining work at the same rate per unit of work?
Q10Exam PatternMedium
A's efficiency is twice that of B. If A and B together can complete a project in 9 days, how many days will B alone take to complete it?
Q11Exam PatternMedium
A worker is paid ₹500 per day. If he works for 18 days and completes 3/4 of a project, what is his total wage for completing the entire project at the same daily rate?
Q12Exam PatternMedium
A contractor hires workers at ₹400 per day. If 5 workers complete a project in 16 days, how much total wage must be paid if the same project is to be completed in 10 days using workers at the same daily rate?
Q13Exam PatternHard
A contractor hires workers to complete a bridge in 20 days. After 5 days, he realizes the work is only 15% complete. He then increases the workforce by 60%. How many additional days beyond the original 20 days will be needed to finish the project?
Q14Exam PatternHard
A can complete a project 40% faster than B. If both work together, they can finish the project in 12 days. In how many days can A alone complete the project?
🔓